CEA Handle Transportation, Assembly & Installation of Metal Press

CEA Project Logistics (PCN members in Thailand & Myanmar) are experts in project cargo & heavy lift and have a wealth of experience in a wide range of industries. The company were recently contracted for the transportation, assembly and installation of a metal press for a metal stamping and assembly factory in Rayong Province, Thailand.

CEA received a combination of containerised and flat rack OOG cargo to their Cargo Consolidation Facility in Laem Chabang. Each container was unloaded & unstuffed and several sections of the machinery (main bed and tie-rod uprights) were assembled by CEA before transportation.

Marketing & Communications Manager, Earl Brown explains the unloading and installation operations as pictured in the gallery below; “Upon arrival at the factory, the press parts and sections were unloaded and assembled. As several sections were of considerable size and weight, CEA erected a temporary gantry crane to assist with the installation. The crane was placed over a pre-constructed pit which would house the completed press and the bed section was lifted, placed into position and aligned on the pit floor.

Other sections were carefully lifted and moved into place with the crown section being installed last and tie-rods and bolts tightened to complete the assembly of the major sections. The gantry crane was then removed to allow a small mobile crane and elevated work platform to install the smaller parts.”

Upon the completion of the project, both CEA and the client were very happy with the efficiency and expertise of the transportation, assembly and installation.